Construction Projects

Trust, accountability, and transparency.

With more than 40 infrastructure projects either completed, in progress or scheduled to break ground in 2019-2020, the City of Evans has launched "The Road Ahead" infrastructure campaign to help residents track and understand the major improvement efforts throughout the City of Evans.

The campaign is easily recognized by its maize and violet logo and will serve as an indicator of progress throughout the city. When a project is complete, a check will be placed on the logo.

2024 CONCRETE REPLACEMNT PROJECT - Work for the 2024 CONCRETE REPLACEMENT PROJECT consists of removal and replacement of concrete curb & gutter, sidewalk, driveway, cross pans, aprons, and ADA ramps in locations designated by the City’s Project Manager.  Sub-grade repair may be necessary at some locations. The Project Manager will treat each replacement site on a case-by-case basis to determine the best method to correct the unacceptable sub-grade conditions. Class 6 Base Material and Type 2 Nilex Geogrid will be added to the Bid Schedule for use in repairs if needed. 

Concrete Replacement Vicinity Maps  

2024 ASPHALT PATCH PROJECT - Work for the 2024 Asphalt Patch Project consists of (181) One Hundred and Eighty-One asphalt patches of various sizes located throughout the city with patch back depths of 6 inches. Most patches will be patched back over existing sub-grade base material as designated by the City of Evan’s Project Manager. However, some patch locations may require sub-grade repair with either geo-textile grid, or Class 6 base material, or a combination of both products if the sub-grade is unstable. These sub-grade repair locations will be required to be confirmed and inspected by the Project Manager prior to asphalt placement. In addition to the asphalt patches there are also (31) Thirty-one utility manholes and (63) Sixty-three water / SS cleanout valve boxes requiring removal of the concrete collar and manually raising or lowering the valve boxes to grade if needed. All utility valve boxes, or manhole raisings will be surrounded with asphalt instead of concrete. All utility boxes and manholes will need to be inspected prior to asphalt paving operations designated by the City’s Project Manager. 

Asphalt Patch Vicinity Map  

2024 ASPHALT SURFACE TREATMENT PROJECT - Work for the 2024 Asphalt Surface Treatment Project consists of 3/8” chip seal application on multiple local streets throughout the City of Evans. Locations are divided by Subdivisions and are prioritized for installation. All utility collars, and pavement marking symbols shall be protected with tar paper. The paper and tape must be removed once the product is distributed and sealed. There are thermoplastic “Stop Bars” that also require protection at the ends of all roads. There is no striping on any of the roadways to protect or to restripe. 

Surface Treatment Vicinity Maps 

2024 CRACK SEAL PROJECT - Work for the 2024 CRACK SEAL consists of Right-of-Way maintenance in the CITY to include: (1) Preparing and filling the separation between the curb and gutter and asphalt surfaces. (2) Preparing and filling the separation between utility concrete collars and asphalt surface. (3) Preparing and filling the visible existing roadway cracks greater than ½” width with an approved crack sealing material on all streets shown by map in Article 5.0 along the highlighted areas. The priorities for treatment are shown on the top of the vicinity map documents entitled Priority levels and are color coded. 

Crack Seal Vicinity Maps