Completed Projects

2025 Completed Projects

To improve safety and traffic efficiency at the 23rd Avenue / 34th Street intersection, the installation of a four-way traffic signal and four associated pedestrian poles was determined the best course of action for the City to take. This intersection is in the immediate vicinity of two elementary schools and lies in the heart of one of the City's primary commercial corridors.

In 2024, the City contracted Benesch to complete the engineering design for the installation of the signal and the City subsequently worked to procure long lead items necessary for construction. Consistent with the City's competitive bid process, bids were solicited on March 20, 2025. Seven contractors submitted valid bids with Lumin8 Transportation Technologies offering the low bid. Along with the low bid, the City has enjoyed a successful relationship with Lumin8 and the firm has completed several projects in satisfactory fashion for the City in the past. The City Council approved the bid unanimously at the May 6, 2025 regular meeting. 

This project was completed in early September of 2025. 

In 2025, the Evans City Council chose to use funds generated by The Road Ahead 1% sales and use tax to complete three large-scale projects that would provide considerable public benefit. The 2025 major roads projects involved the mill and overlay of both 17th and 23rd Avenues between 32nd and 37th Streets and the full-depth reconstruction of 42nd Street / Prairie View Drive from 35th Avenue to 23rd Avenue.

It was decided that after many minor repairs had been made on collector and neighborhood streets all across the city since the inception of The Road Ahead 1% tax, that upgrades to three of the city’s principal arterial thoroughfares would provide lasting impact on some of Evans’ busiest streets, help attract and retain businesses, and contribute to improving the overall quality of life in the city.

Work began in late April 2025 with concrete replacement work on the shoulders and adjacent sidewalks of 17th Avenue. During the first week of May, the process began to mill & overlay 17th Avenue; work was completed on May 16. A nearly identical process was used on 23rd Avenue, with work on that roadway being completed in early June. 

The full-depth reconstruction of 42nd Street / Prairie View Drive was a more complex project that took considerably longer to complete. The project required the removal of the decaying asphalt surface as well as the road base, and rehabilitation of the subgrade. Concrete work along the center median and curb and gutter areas was also completed. A new road base and asphalt surface was poured. Work wrapped up on this project in early November 2025. 

In planning for these 2025 projects, $5,000,000 was initially budgeted for the work on 17th and 23rd Avenues and 42nd Street. After soliciting bids, the Evans City Council voted to approve a contract with Martin Marietta on Jan. 21, 2025 for a not-to-exceed amount of $4,105,300. In line with the city’s new procurement policies, a subsequent contract with RockSol Consulting Group for $163,462.06 to serve as construction manager for the projects was approved on March 4, 2025. After approval of these contracts, the city had $731,237.94 remaining in the budget for 2025 Major Roads Projects, that amount will be carried forward into 2026 for further work on major segments of the city's surface transportation network. 

23rd Avenue looking south from 34th Street following the completion of mill & overlay work.

The replacement of the aging and obsolete equipment at Renaissance Park - located at 3501 Sienna Avenue in the Tuscany subdivision - had been in the planning stages for the last couple of years. As part of the commitment to furthering the evolution of Evans into a community of choice, improvements at our city parks and public spaces is a high priority. 

In late 2024 and early 2025, city staff solicited quotes and design proposals for qualified vendors. Following review of the submitted proposals, the city selected GameTime Altitude based on the firm's proven record, responsiveness, and successful past projects in Evans. 

GameTime Altitude presented several different design concepts to the Evans Parks and Recreation Advisory Board, who reviewed the proposals and made a recommendation to the city council. On June 3, 2025, the city council approved the design proposal that was recommended from the advisory board. 

This project had a budget of $750,000 for the new playground equipment, pour-in-place soft surface, the removal of the old playground components, and installation of the new equipment. The funds for this project came from the city's Conservation Trust Fund, which derives its balance from proceeds from the Colorado Lottery that are disbursed by the State of Colorado to municipalities for parks, open space, and conservation projects. 

The old playground was disassembled in August 2025 and the city will attempt to sell the components at auction. The project was completed in November 2025 and an official ribbon cutting ceremony led by Evans Mayor Mark Clark and Councilmen Jeff Crabtree and Chris Delaney took place on Nov. 19. 

As Evans continues to invest in parks and public spaces - aiming to improve quality of life and foster community connectedness - another milestone was reached in 2025 with the completion of Hunter's Reserve Park at 3800 29th Avenue. This project transformed what was an empty field next to a stormwater detention pond into an active neighborhood park complete with a small playground, walking trail, picnic pavilion, and large open lawn space. 

This project got underway on May 7, 2024 when the Evans City Council selected a proposal from BrightView Landscape Development to develop the formerly vacant space into a public park. At the March 18, 2025 Evans City Council meeting, unanimous approval was given to the final design concept and associated contract with BrightView for a not-to-exceed amount of $817,391.66. 

This project was funded by Park Impact Fees - fees paid by new development to supplement increased demand for public services caused by population increases - and construction began in May 2025. The project was completed in October 2025. 

 

2024 Completed Projects

Work for the 2024 Asphalt Reconstruction Project consists of (4) four separate projects.

The first project will be a full asphalt reconstruction of 15th Avenue from 37th Street to 34th Street, the second project will be a full asphalt reconstruction of 41st Street from Belmont Avenue to 17th Avenue, the third project will be a full asphalt reconstruction of 41st Street Road from Belmont Avenue to 17th Avenue. The fourth project additional alternate No. 1 will consist of a full asphalt reconstruction of a section of Heather Lane from Phlox Lane to Primrose Lane. 

Project # 1 will consist of full asphalt reconstruction of 15th Avenue from 37th Street to 34th Street. The roadway is believed to be (4”) four-inch thickness of asphalt mat over (8”) eight-inch Class 6 Base Material. In-situ earthen material is sandy clay loam.

Work for Project # 1 (15th Avenue) of the 2024 Asphalt Reconstruction Project consists of roto-milling the entire surface of existing asphalt pavement estimated to be four (4") inches in depth, removal of (6”) six inches of in-situ sub-grade material, scarification, compaction and grading of earthen in-situ sub-grade material, installing a (6”) six-inch Class 6 base course layer (crushed concrete is not a suitable replacement product and will be strictly refused), compaction and grading of base course layer, soil sterilization of entire surface of the base course layer, placement of a (2”) two inch bottom lift hot mix asphalt Grading S, SP 64-22, installing an emulsified tack layer, placement of a (2”) two inch top lift hot mix asphalt Grading S, SP 64-22, adjusting of existing water valves, sanitary sewer manholes, and storm drain manholes which are to be ¼” inch below the asphalt surface.  Concrete collars will not be installed around existing utility box structures and manholes, instead the existing concrete collars will be removed, and the utilities will be raised to grade prior to paving and asphalt will surround the utility boxes and manholes, installing (2’) two-foot wide thermoplastic stop bars at stop sign intersections as dictated.

The City of Evans recognizes that the project is located on a local collector street with accessibility concerns for the residents during construction. There are (31) thirty-one single family homes that encompass the project. This site is also near a school, so summer construction is necessary. We will need to keep access open throughout the project, but do not want the increased traffic a school will surely bring when it is in session.

Project # 2 will consist of full asphalt reconstruction of 41st Street from Belmont Street to 17th Avenue. The roadway is believed to be (2 1/2”) two and a half-inch thickness of asphalt mat over (3”) three-inch Class 6 base material. In-situ earthen material is sandy clay loam.

Work for Project # 2 (41st Street) of the 2024 Asphalt Reconstruction Project consists of roto-milling the entire surface of existing asphalt pavement estimated to be two and a half (2 ½”) inches in depth, removal of (7 ½ ”) seven and a half inches of in-situ sub-grade material, scarification, compaction and grading of earthen in-situ sub-grade material, installing a (6”) six inch Class 6 base course layer (crushed concrete is not a suitable replacement product and will be strictly refused), compaction and grading of base course layer, soil sterilization of entire surface of the base course layer, placement of a (2”) two inch bottom lift hot mix asphalt Grading S, SP 64-22, installing an emulsified tack layer, placement of a (2”) two inch top lift hot mix asphalt Grading S, SP 64-22, adjusting of existing water valves, sanitary sewer manholes, and storm drain manholes which are to be ¼” inch below the asphalt surface. Concrete collars will not be installed around existing utility box structures and manholes, instead the existing concrete collars will be removed, and the utilities will be raised to grade prior to paving and asphalt will surround the utility boxes and manholes, installing (2’) two-foot wide thermoplastic stop bars at stop sign intersections as dictated.

The City of Evans recognizes that the project is located on a local collector street with accessibility concerns for the residents during construction. There are (14) fourteen single family homes that encompass the project. We will need to keep access open throughout the project.

Project # 3 will consist of full asphalt reconstruction of 41st Street Road from Belmont Street to 17th Avenue. The roadway is believed to be (2 ½”) two and a half-inch thickness of asphalt mat over (3”) three-inch Class 6 base material. In-situ earthen material is sandy clay loam.

Work for Project # 3 (41st Street Road) of the 2024 Asphalt Reconstruction Project consists of roto-milling the entire surface of existing asphalt pavement estimated to be two and a half (2 ½”) inches in depth, removal of (7 1/2”) seven and a half inches of in-situ sub-grade material, scarification, compaction and grading of earthen in-situ sub-grade material, installing a (6”) six inch Class 6 base course layer (crushed concrete is not a suitable replacement product and will be strictly refused), compaction and grading of base course layer, soil sterilization of entire surface of the base course layer, placement of a (2”) two inch bottom lift hot mix asphalt Grading S, SP 64-22, installing an emulsified tack layer, placement of a (2”) two inch top lift hot mix asphalt Grading S, SP 64-22, adjusting of existing water valves, sanitary sewer manholes, and storm drain manholes which are to be ¼” inch below the asphalt surface. Concrete collars will not be installed around existing utility box structures and manholes, instead the existing concrete collars will be removed, and the utilities will be raised to grade prior to paving and asphalt will surround the utility boxes and manholes, installing (2’) two-foot wide thermoplastic stop bars at stop sign intersections as dictated.

The City of Evans recognizes that the project is located on a local collector street with accessibility concerns for the residents during construction. There are (15) fifteen single family homes that encompass the project. We will need to keep access open throughout the project.

Add Alt # 1 Project # 4 (Heather Lane) of the 2024 Asphalt Reconstruction Project will consist of full asphalt reconstruction of Heather Lane from Phlox Lane to Primrose Lane. The roadway is believed to be (5 1/2”) five and a half-inch thickness of asphalt mat over In-situ earthen material. In-situ earthen material is clay.

Work for Project # 4 (Heather Lane) of the 2024 Asphalt Reconstruction Project consists of roto-milling the entire surface of existing asphalt pavement estimated to be five and a half (5 ½”) inches in depth, removal of (4 ½”) four and a half inches of in-situ sub-grade material, scarification, compaction and grading of earthen in-situ sub-grade material, installing a (6”) six inch Class 6 base course layer (crushed concrete is not a suitable replacement product and will be strictly refused), compaction and grading of base course layer, soil sterilization of entire surface of the base course layer, placement of a (2”) two inch bottom lift hot mix asphalt Grading S, SP 64-22, installing an emulsified tack layer, placement of a (2”) two inch top lift hot mix asphalt Grading S, SP 64-22, adjusting of existing water valves, sanitary sewer manholes, and storm drain manholes which are to be ¼” inch below the asphalt surface. Concrete collars will not be installed around existing utility box structures and manholes, instead the existing concrete collars will be removed, and the utilities will be raised to grade prior to paving and asphalt will surround the utility boxes and manholes, installing (2’) two-foot-wide thermoplastic stop bars at stop sign intersections as dictated. The City of Evans recognizes that the project is located on a local collector street with accessibility concerns for the residents during construction. There are (15) fifteen single family homes that encompass the project. We will need to keep access open throughout the project.

The City of Evans recognizes that the project is located on a local collector street with accessibility concerns for the residents during construction. There are (5) five single family homes that encompass the project. We will need to keep access open throughout the project.

Geotextile Grid is included in the contract in the event unstable sub-grade material is encountered. All QC (Quality Control) testing is to be considered inclusive of costs for compaction of each respective layer of street section whether it is asphalt, base material, fly-ash or earthen in nature. Traffic control is broken out as a separate line item and not included in the mobilization costs.

2024 Asphalt Reconstruction Vicinity Map

2024 Concrete Replacement - The 2024 concrete replacement project consists of removal and replacement of concrete curb & gutter, sidewalk, driveway, cross pans, aprons, and ADA ramps in locations designated by the City’s Project Manager. Sub-grade repair may be necessary at some locations. The Project Manager will treat each replacement site on a case-by-case basis to determine the best method to correct the unacceptable sub-grade conditions. Click on the link to view the maps of locations of concrete replacement work completed in 2024.

2024 Concrete Replacement Maps

2024 Crack Seal Project - The 2024 crack seal project consists of right-of-way maintenance in the City of Evans to include: (1) preparing and filling the separation between the curb and gutter and asphalt surfaces, (2) preparing and filling the separation between utility concrete collars and asphalt surface, (3) preparing and filling the visible existing roadway cracks greater than ½” width with an approved crack sealing material on all streets shown by map in Article 5.0 along the highlighted areas. The priorities for treatment are shown on the top of the vicinity map documents entitled priority levels and are color coded. Click on the link to view the maps of locations of crack seal work completed in 2024.  

Crack Seal Vicinity Maps

2024 Asphalt Patch Project - Work for the 2024 Asphalt Patch Project consisted of (181) one hundred and eighty-one asphalt patches of various sizes located throughout the city with patch back depths of 6 inches. Most patches will be patched back over existing sub-grade base material as designated by the City of Evan’s Project Manager. However, some patch locations may require sub-grade repair with either geo-textile grid, or Class 6 base material, or a combination of both products if the sub-grade is unstable. These sub-grade repair locations will be required to be confirmed and inspected by the Project Manager prior to asphalt placement. In addition to the asphalt patches there are also (31) thirty-one utility manholes and (63) sixty-three water / SS cleanout valve boxes requiring removal of the concrete collar and manually raising or lowering the valve boxes to grade if needed. All utility valve boxes, or manhole raisings will be surrounded with asphalt instead of concrete. All utility boxes and manholes will need to be inspected prior to asphalt paving operations designated by the City’s Project Manager.

Asphalt Patch Vicinity Maps

Work for the 2024 Asphalt Surface Treatment Project consisted of 3/8” chip seal application on multiple local streets throughout the City of Evans. Locations are divided by subdivisions and are prioritized for installation. All utility collars, and pavement marking symbols shall be protected with tar paper. The paper and tape must was removed once the product is distributed and sealed. There are thermoplastic “stop bars” that also require protection at the ends of all roads. There is no striping on any of the roadways to protect or to restripe. 

2024 Asphalt Surface Treatment Maps

Work for the 2024 EVO Radar Sensor Project consisted of installation  of eight  (8) Econolight EVO Radar Sensors at all City of Evans traffic signals except 37th Street and 65th Avenue.

The intersections for installation are:

  • 37“ Street and 11th Avenue
  • 32nd Street and 11th Avenue
  • 37th Street and 17th Avenue
  • 37th Street and 23trd Avenue
  • 32nd Street and 23“' Avenue
  • 37th Street  and 29" Avenue
  • 37th Street and 35th Avenue
  • 34th Street and 34th Avenue.

Installation required the removal of all existing ITS Plus Cameras, wiring, and video card components from the intersections. Capping of open holes on the existing mast arms is a requirement. New holes were drilled /cored through Evo (2) poles at each intersection at each radar location. Econolight supplied a representative to guide the contractor with the best location and height for each radar mount.

Once all wire was removed and conduits cleared, the existing conduit was used to rewire the new EVO Radar systems. New wire was pulled through the conduit using the old wire as a fish tape to pull through). All components for the Radar system (brackets, radar hub, and radars) were purchased for the new installations. Radar hubs were mounted in the traffic signal cabinet and connected to the existing Econolight Cobalt Controllers. The Econolight representative assisted and guide the contractor to program the new radar units. The City of Evans also had our traffic engineer available to answer any questions.

2024 EVO Radar Installation Location Maps

Contact Us

1100 37th Street
Evans, Colorado 80620

Phone: 970-475-1170
Fax: 970-475-1190
Office hours (Monday to Friday): 8:00am – 5:00pm

Subscribe to City News Alerts and the Evans Express

Stay up to date on the city's activities, events, programs, and operations by subscribing to our eNewsletters.